BELGIUM: CERTIFICATION MISSION ACCORDING TO INTEROPERABILITY AND NATIONAL REGULATIONS

Klant

Infrabel

Subsysteem

Control, Command and Signalling

Duur van het project

2016-2020

Beschrijving van het project

CERTIFER’s personnel:

1 project manager & 6 assessors

Project’s description:

modernisation project of 67 km of railway line Hatrival – Luxembourg border that includes:

Infrastructure modernisation:

  • 5 curves
  • 6 level crossing
  • 27 structures in total
  • 7 railway stations

Signalling subsystem

Signalling system modernization and adaptation to higher trains speed

Energy subsystem

Dismantling existing catenary 3kV and construction of new overhead catenary system 25kV

Omvang van het werk

CERTIFER’s service

NoBo service

  • Energy: interoperability assessment of the Energy subsystem according to TSI 1301/2014;
  • Infrastructure: interoperability assessment of the Infrastructure subsystem according to TSI Infra 1299/2014;
  • PRM: interoperability assessment of the PRM subsystem according to TSI Energy 1300/2014.

DeBo service

  • CCS & Infrastructure : assessment of the Signalling and Infrastructure systems according to national rules.
Prestaties/ Succes
Alles bekijken
France: haut-bugey conventional line
France: Eole project
NoBo/DeBo FR/AsBo Services
France: CDG express line assessment
DeBo/NoBo/AsBo Services
France: bypass of Donges industrial sites
NoBo, DeBo and AsBo service
France : Bretagne Pays-De-La-Loire (BPL) HSL
Evaluation of the TGV POS subsystem in relation to TSI
Baltic Countries: Rail Baltica Project
NoBo/AsBo service
Denmark: Ringsted – Fehmarn
NoBo / ISA Services

Heeft u een project?

Heeft u expertise nodig voor uw spoorwegproject?

Bent u een mobiliteitsexpert?

Sluit u zich aan bij ons team om aan innovatieve projecten te werken en samen de toekomst van mobiliteit te bevorderen.