ALGERIA: LIGHT RAIL TRAIN OF OUARGLA

Cliente

EMA

Sottosistema

Durata del progetto

2015- 2017

Descrizione del progetto

The first tramway line of Ouargla is 12.6 km long with 23 stations, 16 junctions, 2 park-and-ride lots and 3 interchange poles. It connects El Ksar (the old city) to the new city (Hai Nasr).

Ambito di lavoro

This assessment service applies to the following subsystems:

  • Global system coherence, system approach
  • Railway signalling and control,
  • Rolling stock,
  • Operation/maintenance of tramways,
  • Electrical traction energy / Traction energy substation and traction current return circuit,
  • External risks, natural and technological risks,
  • Railway track, platform and switches and crossings
  • Civil engineering-solidity
Risultati
Vedi tutto
France: haut-bugey conventional line
France: Eole project
NoBo/DeBo FR/AsBo Services
France: CDG express line assessment
DeBo/NoBo/AsBo Services
France: bypass of Donges industrial sites
NoBo, DeBo and AsBo service
France : Bretagne Pays-De-La-Loire (BPL) HSL
Evaluation of the TGV POS subsystem in relation to TSI
Baltic Countries: Rail Baltica Project
NoBo/AsBo service
Denmark: Ringsted – Fehmarn
NoBo / ISA Services

Hai un progetto?

Hai bisogno di un supporto professionale per il tuo progetto ferroviario?

Sei esperto nel settore mobilità?

Unisciti al nostro team per lavorare su progetti innovativi e far progredire insieme il futuro della mobilità.