AUSTRALIA: NORTHWEST METRO OF SYDNEY

Kunde

TfNSW

Teilsystem

Dauer des Projekts

2014 to 2020

Beschreibung des Projekts

The North West Rail Link (NWRL) Project is a vast, and complex project which final objective is to provide Sydney, and New South Wales, with a major system. The Client, Transport for New South Wales (TfNSW), subdivided the NWRL project in three main contracts; a Civil Works one for civil engineering & viaducts, a Civil Works for tunnels & stations, and a Public-Private
Partnership (PPP) contract for the trains’ and systems’ operation. TfNSW also made contractual agreements with several stakeholders in order to facilitate the delivery of the NWRL project.
The SYSTRA / GHD Joint Venture is involved in the Certification Mission within the PPP contract for the Design, Manufacturing & Delivery Liability Period (DLP) phases.
The project includes:

  •  23 km of track works and 8 new stations
  •  13 km of existing upgraded lines with 5 upgraded existing railway stations, from Epping to Chatswood
  •  20 new trains
  •  The fully automated railway system in Australia
  •  NWRL is the biggest common transportation project in Australia, and should be commissioned by the end of 2019.

Umfang der Arbeiten

SYSTRA/GHD has been contracted as an Independent Certifier for the following disciplines:

  •  Operation & Maintenance;
  •  Rolling Stock to CERTIFER
  •  Workshop & Depots
  •  Power Supply & Catenary system
  •  CBTC
  •  Stations & buildings
  •  Infrastructure & Civil Works

Key activities within the IC contract include:
Monthly reporting to project stakeholders on project progress and key risks;
Elaborate a risk-based system approach for verification, monitoring and reporting activities;
Issue of Independent Certifier Certificates for around 800 technical design packages covering the scope of works during the 3 stages of the Design phase (Preliminary, Substantial and Final);
Monitor/certify key surveillance during the construction phase until the testing and commissioning of the line.
The Independent Assessment leads to the issuing of a judgment, distinct & independent from any personal design, development or operating system, showing that this system meets all the contractual requirements.

Errungenschaften
Siehe alle
France: haut-bugey conventional line
France: Eole project
NoBo/DeBo FR/AsBo Services
France: CDG express line assessment
DeBo/NoBo/AsBo Services
France: bypass of Donges industrial sites
NoBo, DeBo and AsBo service
France : Bretagne Pays-De-La-Loire (BPL) HSL
Evaluation of the TGV POS subsystem in relation to TSI
Baltic Countries: Rail Baltica Project
NoBo/AsBo service
Denmark: Ringsted – Fehmarn
NoBo / ISA Services

Haben Sie ein Projekt?

Benötigen Sie fachkundige Unterstützung für Ihren Eisenbahnprojekten?

Sind Sie ein Mobilitätsexperte?

Kommen Sie in unser Team, um an innovativen Projekten zu arbeiten und die Zukunft der Mobilität gemeinsam voranzutreiben.